Equipment
Fouling
An example of equipment fouling limiting
the product RVP occurred in an FCCU debutanizer. The overhead product is a mixture of olefinic and
paraffinic C3 and C4’s. The bottom
product is FCCU gasoline used as a gasoline
blendstock.
Additional operating data illustrated how the overhead condensing capacity
limited the debutanizer operation. The hot vapor bypass
pressure control valve operated nearly closed. Attempts to
increase the reflux rate only resulted in the hot vapor bypass
control valve closing and the tower pressuring up. The maximum
reflux rate of 11.2 MBPSD was 23% below design. The calculated
overhead condenser duty was only 23.8 compared to the 29.1
MMBTU/hr design duty. The process outlet was only 111° F
compared to the 100° F design even though the actual cooling
water supply temperature was 15° F colder than design. The
calculated overall heat transfer rate was only 44.3 compared
to the 124 design. Obviously, the overhead system was not
performing per design.
The lower than design reflux rate raised
the butane concentration in the FCCU gasoline from the design
value of 0.05 LV% up to 0.7 LV% and greater. The higher butane
concentrations resulted in higher FCCU gasoline RVP’s. FCCU
gasoline’s large gasoline pool percentage made meeting the
refinery’s finished gasoline specifications difficult. Since
FCCU capacity was the major refinery limit, the debutanizer
overhead condensing limit had a large, detrimental impact upon
refinery profitability.
The importance of the operating bottleneck
lead to further analysis. All evidence of the poor condenser
operation pointed to tube side cooling water fouling. The much
lower than design heat transfer coefficient indicated fouling
on either the tube or shell sides of the exchanger. The
cooling water rate was measured by injecting a known amount of
tracer into the exchanger inlet and calculating the water flow
rate from the concentration of the tracer in the exchanger
outlet. The calculated flow rate of 1,279 gpm cooling water
rate was 60% below the 2,292 gpm design flow rate. The cooling
water rate was below design despite the fact that the
exchangers had 22 psi available pressure drop as compared to
only 8 psi in the original design.
The curve comparing the
overhead condenser heat transfer with the RVP attainable
illustrates how much the overhead condenser fouling affects
the bottoms RVP. The base case operation reflecting the survey
conditions is shown at the lower left of the curve. The
minimum simulation RVP attainable is 7.3 with essentially no
C4- in the bottoms. The other data points on the
same line indicate how much the gasoline RVP increases as the
overhead condenser heat transfer coefficient is reduced. All
of the points below the dashed line denoting the survey U of
44 represent feasible operating points. The top curve
estimates the effect of higher cooling water temperatures and
hence RVP’s in the summer. Almost all of the points are above
the existing U dashed line indicating that the operation is
unfeasible with the fouled exchangers. All of the runs
maintained the same 1.7 LV% C5+ in the overhead
LPG.
The curve clearly shows how much the
survey heat transfer coefficient was below design. The curve
for the current winter operation indicates that the RVP could
be reduced only marginally by removing all of the
C4-. The curve for summer operation shows the large
impact that the poor heat transfer coefficient would have in
the coming months. Assuming that the exchanger heat transfer
coefficient remained constant, the fouled overhead condensers
would result in FCCU gasoline RVP’s above 12. This
unacceptably high RVP forced a resolution.
Attempts at online cleaning were
unsuccessful. A shutdown was required to clean the bundles. To
minimize the expensive downtime, new bundles were bought in
advance. The debutanizer was shutdown, and the new bundles
were installed. The existing bundles indicated severe tubeside
fouling as was expected. Upon startup, the condenser operation
returned to design conditions, and the debutanizer no longer
limited unit and refinery operation. Lower FCCU gasoline RVP’s
helped meet the mandated pool specifications.
Minor Equipment
Debottlenecking
Return to Main Article
Page